Voyage estimate
Suezmax voyage: Esmeraldas to Philadelphia
A Suezmax carrying 130,000 tonnes from Esmeraldas to Philadelphia sails about 10,560 nm laden via the Strait of Magellan, about 35.2 days at 12.5 knots. With the ballast leg back and 4 days in port, the round voyage takes about 47.0 days and burns about 1,767 tonnes of fuel.
Round voyage
47.0 d
35.2 d laden
Laden distance
10,560 nm
Avoiding the Panama Canal
Fuel (VLSFO)
1,767 t
Round voyage
CO2
5,568 t
Outside EU ETS
Round voyage breakdown
| Leg | Distance | Speed | Days | Fuel |
|---|---|---|---|---|
Laden Esmeraldas → Philadelphia | 10,560 nm | 12.5 kn | 35.2 | 1,408 t |
Ballast Philadelphia → Esmeraldas | 2,448 nm | 13 kn | 7.8 | 259 t |
Port time Loading and discharge | — | — | 4.0 | 100 t |
| Round voyage | 13,008 nm | 47.0 | 1,767 t |
Laden via the Strait of Magellan; ballast via the Panama Canal.
A laden Suezmax draws about 17 m, deeper than the Panama Canal's 15.2 m limit, so the laden leg takes a longer route: avoiding the Panama Canal.
Emissions and EU ETS
The round voyage burns about 1,767 tonnes of VLSFO, emitting about 5,568 tonnes of CO2. Neither port is in the EU ETS area, so no EU allowances are needed for this voyage.
Assumptions
- Cargo
- 130,000 t
- Laden speed
- 12.5 kn at 40 t/day
- Ballast speed
- 13 kn at 33 t/day
- Port time
- 4 days at 25 t/day
- Laden draft
- 17 m
- CO2 factor
- 3.151 t per t fuel
Other ship sizes on this route
Questions
How long does a Suezmax take from Esmeraldas to Philadelphia?
About 35 days 5 hours laden at 12.5 knots over 10,560 nm via the Strait of Magellan. The full round voyage, with the ballast leg back and 4 days in port, takes about 47.0 days.
How much fuel does a Suezmax burn on this voyage?
About 1,767 tonnes of VLSFO for the round voyage (1,408 t laden, 259 t ballast, 100 t in port), emitting about 5,568 tonnes of CO2.