Notice of Readiness

NOR

Meaning

A notice of readiness (NOR) is the master's formal notice that the ship has arrived and is ready in every respect to load or discharge.

Also written as NOR tendered

Notice of Readiness explained

The NOR is what starts the laytime process. It is tendered by the master or agent to the charterer, shipper or receiver once the ship has reached the place the charter requires, usually the customary anchorage or within port limits, and is physically and legally ready to handle cargo.

On most tanker terms laytime then starts after a notice period, commonly six hours, or when the ship is all fast at the berth if that happens first. An NOR given too early, before the ship has arrived or while it is still not ready, may be invalid and can leave the owner with no laytime running at all.

Example

A Suezmax anchors at the customary anchorage at 0600, tenders NOR at 0615, and berths the next day at 1400. Laytime starts at 1215, six hours after NOR, not at berthing.

Watch out for

An invalid NOR is not cured by the charterer starting cargo operations unless the charter or the facts amount to a waiver. Many owners re-tender NOR at every material change, such as on obtaining free pratique, to protect themselves.